Phase 1A - Lake Mead Boulevard to Carey Avenue
The construction was authorized in January 2009 and is complete.
Phase 1B - Owens Avenue to Lake Mead Boulevard
The construction was authorized in January 2010 and is underway.
Phase 1C - bridge from Carey Avenue to Losee Road
The design is complete. Bidding is anticipated to commence in Fall 2010, with a estimated construction start at the beginning of 2011.
Phase 1D - bridge and improvements from Losee Road to Brooks Avenue
The final design is underway and expected to be completed in 2011. A construction schedule has not been established at this time.
North 5th Street Planning Study - Cheyenne Avenue to Northern Beltway
In an effort to develop concept plans and alternates for future development, the City completed a preliminary engineering planning study, north of the project area, which is complete. The design and construction of future improvements north of Cheyenne Avenue will be the responsibility of property owners as a standard off-site improvements requirement of development. The alternatives and recommendations developed in the planning study are conceptual only.
To view updated layouts for the Owens Avenue to Cheyenne Avenue section, visit our Project Information page. |